Connect Operation to Alternate Routing
This procedure is used to connect an operation to alternative routings.
Before You Start
Before you connect an operation to other routings, the following prerequisites must be met:
- Alternate routings must be entered in 'Alternate Routing. Open' (PDS035).
- The field Alt Routings in panel E in 'Service. Connect to Facility' (MOS301) must have option 1 or 2 specified.
Follow These Steps
-
Select 'Service. Open' (MOS300).
-
Specify option 12='Product Structure' for the product which will contain the alternate routings. This starts 'Product. Connect Materials/Operations' (PDS002).
-
Specify option 17='Alt routing / op' for the operation to be connected to one or more alternate routings. This starts 'Operation. Connect Alternate Routings' (PDS008).
-
Specify the alternate routings in which the operation will be included. Press Enter to save.
-
To connect more operations to alternate routings, go to step 2. Otherwise, end the program using F3 = End.
Outcome
The result of this procedure is the creation of alternate routings.