WO rescheduling - MOS015
The auto start job 'Reschedule WO' (MOS015) monitors the request for re-planning of manufacturing orders and re-plans accordingly.
Programs that create records in the ASJ table MMO015
| Program | Description |
|---|---|
| MOS010 | Maintenance Order - WO. Reschedule |
| MOS020 | WO Operation. Reschedule |
| MOS025 | Combined reschedule |
| MOS195 | Work order scheduling |
| MOS985 | Replan MO after operation finish report |
| RPS002 | Action Message. Open per Item |
| MOMNGWOP | Manage work orders. Function program |
Input parameters - MMO015
| Field name | Description | Size |
|---|---|---|
| ZAJNU | Job number | 6,0 |
| ZAPRD | Job date | 6,0 |
| ZAPRT | Job time | 6,0 |
| ZACONO | Company | 3,0 |
| ZATTYP | Stock transaction type | 2,0 |
| ZAPGNM | Program name | 10 |
| ZAJNA | Job name | 10 |
| ZARGDT | Entry date | 8,0 |
| ZARGTM | Entry time | 6,0 |
| ZACHID | Changed by | 10 |
| ZATSTM | Timestamp | 26 |
Input parameters - MMO010
| Field name | Description | Size |
|---|---|---|
| ZAJNU | Job number | 6,0 |
| ZAPRD | Job date | 6,0 |
| ZAPRT | Job time | 6,0 |
| ZAFACI | Facility | 3 |
| ZAPRNO | Product number | 15 |
| ZAMFNO | Manufacturing order number | 7,0 |
| ZAOPNO | Operation number | 4,0 |
| ZAFIDT | Finish date | 8,0 |
| ZASTDT | Start date | 8,0 |
| ZAMSTI | Start time | 4,0 |
| ZAMFTI | Finish time | 4,0 |
| ZALTRE | Lead-time reduction | 3,0 |
| ZAORQA | On order alternate U/M | 15,6 |
| ZAMAUN | Manufacturing U/M | 3 |
| ZAPRIO | Priority | 1,0 |
| ZAWLDE | Load dependent | 1,0 |
| ZANSOP | Operation split not allowed | 1,0 |
| ZARPLL | Re-scheduling lower levels | 1,0 |
| ZARPOE | Re-scheduling upstream operations | 1,0 |
| ZARPOA | Re-scheduling downstream operations | 1,0 |
| ZAPRLO | Product number overlying level | 15 |
| ZAMFLO | MO-number higher level | 7,0 |
| ZAMSLO | Serial number overlying level | 4,0 |
| ZAPROB | Product number | 15 |
| ZAMFOB | Manufacturing order number | 7,0 |
| ZAOPOB | Operation number | 4,0 |
| ZALEVL | Lowest level | 2,0 |
| ZALVSQ | Level sequence | 3,0 |
| ZADONE | 1,0 | |
| ZATTYP | Stock transaction type | 2,0 |
| ZAPGNM | Program name | 10 |
| ZARGDT | Entry date | 8,0 |
| ZARGTM | Entry time | 6,0 |
| ZALMDT | Change date | 8,0 |
| ZACHNO | Change number | 3,0 |
| ZACHID | Changed by | 10 |
| ZANFAC | New facility | 3 |
| ZADEFR | Defer work order | 1,0 |
| ZAMRES | Material reservation | 1,0 |
| ZASTD2 | Start date | 8,0 |
| ZAMVA1 | Meter value 1 | 15,6 |
| ZAMVA2 | Meter value 2 | 15,6 |
| ZAMVA3 | Meter value 3 | 15,6 |
| ZAMVA4 | Meter value 4 | 15,6 |
Updated tables
| Table | Description | |
|---|---|---|
| MMO01010 | Start record for change/delete MO | |
| MMO01015 | Start record for change/delete MO | |
| MMOHED00 | Work order header | |
| MMOHED40 | Work order header | |
| MMOOPE00 | WO operations |
Related ASJs and functions
| Name | Description | |
|---|---|---|
| ASJ: | None | |
| Functions: | MOS900 | Calculate quantities of WO |
| MOS905 | Calculate lead time on WO | |
| PMS910 | Remove workload |