Enter Bill of Resources
This procedure is used to enter resource requirements connected to a resource requirements profile.
Before you start
To start this procedure, these prerequisites must be met:
- The facility is entered in 'Facility. Open' (CRS008). Note that a facility can have several warehouses.
- Work centers with resource type 4 or 5 are entered.
Follow these steps
-
Start 'Resource Reqmnt Profile. Open' (RCS030). Select the profile to process using option 11, or create a new profile. 'Resource Structure. Open' (RCS031) is displayed.
-
Enter the first resource. Only resources with type 4 or 5 can be entered.
-
In the Lead time offset field, specify the number of days before the finish date the resources should be loaded. This field is updated automatically when using dynamic lead-time calculation.
-
Enter the capacity. The capacity unit used is the same as for measuring capacity and load. For labor-time work centers, the labor time must be used.
-
To create a lead time allocated resource profile, enter different values for Lead time offset and Resource usage. Repeat this step until the profile is complete for the period in question.