Supply Lead Time
This document explains the settings for supply lead-time. The management of the supply lead time depends on the acquisition code in (MMS002/E).
If the acquisition code is 1 = Manufactured item, the supply lead time is calculated by the system according to the product structure and the capacity in the work centers.
If the acquisition code is 2 = Purchased item, the supply lead time can be updated manually in (MMS002/E) or for the main supplier in (PPS040/E).
If the acquisition code is 3 = Distribution from another warehouse, the supply lead time is updated manually in (MMS002/E).
Outcome
The supply lead time is set.
- Queue time, setup time, run time, move time, inspection time and put-away time are set for a manufactured item.
- For a purchased item, the supply lead time can either be a general lead time (include all lead time components) or just the supplier lead time.
- Used as a lead time component to calculate the total lead time per item/warehouse connection.
Supply lead time is specified per item (MBLEA1/MITBAL). For purchased items it is retrieved from via supplier file (IFLEA1/MITVEN)
Before you start
- Basic data for items and inventory must have been set.
- Product structure 'Product Structure. Open' (PDS001) and work-center capacity 'Work Center. Open' (PDS010) must have been set.
- Suppliers must have been connected to items in 'Supplier. Connect Item' (PPS040).
Parameters to set
Program ID/Panel | Field | The field indicates … |
---|---|---|
(PDS001/E) | Supply lead time |
Acquisition code is 1 = Manufactured item (MMS002/E) The supply lead time for manufactured items is calculated by the system according to the product structure and the capacity in the work center. |
(MMS002/E) | Supply lead time |
Acquisition code is 2 = Purchased item, or 3 = Distributed between two warehouses. These acquisition codes (2 and 3) open up this field. The lead time can be filled in directly here. For acquisition code 2 it is also possible to calculate the supply lead time in (PPS040) as below. |
(PPS040/E) | Supply lead-time |
Acquisition code is 2 = Purchased item (MMS002/E) The supply lead time for purchased items is entered per supplier/item, either in working days (5) or ordinary calendar days (7). This is set in 'Settings - Purchasing' (CRS780/G) on parameter 33. |
Follow these steps
Supply lead time for manufactured items
-
Start 'Product. Open' (PDS001), enter the E panel. The value in the 'Supply lead time' field is calculated considering the order quantity, the setup and run times and the queue times between the operations.
-
After the calculation is done the field is updated on the (MMS002/E) panel.
Supply lead time for purchased items
-
Start 'Item. Connect Warehouse' (MMS002), enter the E panel and fill in a general supply lead time for the item/warehouse combination or
-
Start 'Supplier. Connect Item' (PPS040) and fill in the 'Supply lead time' field for the main supplier.
Supply lead-time for items distributed between two warehouses
-
Start 'Item. Connect Warehouse' (MMS002), enter the E panel and fill in a supply lead-time for the supplying warehouse.