Transmission Lead Time
This document explains how transmission lead time is set. Transmission lead time is only active when the communication with the supplier is by paper. A check is done in the following priority order to find out which communication code the supplier has:
- 'Purchase Order Type. Open (PPS095/E)
- 'Supplier. Connect Item' (PPS045/E)
- 'Document. Connect Partner Reference' (CRS945/E)
If all three sources listed above are blank, the communication code is set to 1= Paper.
Outcome
A lead time is set for mailing a letter (paper) to the supplier.
Transmission lead time is specified per supplier (IDPODA/CIDMAS)
Transmission Lead Time is used as a lead time component to calculate the total lead time per item/warehouse connection.
Before you start
There are no prerequisites before starting.
Follow these steps
-
Start 'Supplier. Open' (CRS620) and go to the E panel. Fill in the 'Transmission lead time' field. The value is entered in days.
-
The transmission lead time is displayed on the (MMS002/G) panel.