Quotation Status Management
This document describes how to manage a quotation from the stage when the completed quotation is reviewed until it is closed or transferred to a project order.
Before you start
A project quotation must have been created in 'Project Quotation. Open' (POS100).
Follow these steps
The section below describes the activities in this process.
- 
            
Reviewing Quotation
By using option 64=review in (POS100) you can set the quotation status to 20=ready for review.
 - 
            
Approving Quotation
By using option 65='Approve quotation' you can set the quotation status to 30=approved.
 - 
            
Printing Quotation
By using option 6=print you can print the quotation and the quotation status is set to 40=printed.
 - 
            
Entering Reply
You enter the quotation reply – positive or negative – for each customer. You can also enter:
- Reason for acceptance/rejection
 - Competitor that was accepted
 - Date order was rejected
 
Quotations that are not processed further are assigned status 99=cancelled. Status 95=postponed indicates that the customer has not decided and will reply later.
 - 
            
Transferring to Project Order
An accepted quotation can be transferred to a project order. The customer automatically becomes a partner, of the type Customer. You can include any of the following information in the transfer:
- Costing transfer to project budget
 - Checklists
 - Product configurations
 - Project information
 - Scheduling.
 
The following processing is done when the quotation structure is copied:
- Elements flagged as both quotation and project elements are copied.
 - Elements flagged as only quotation elements are not copied.
 - Elements flagged as only project elements are copied, even though they are not displayed in the quotation project structure.