Occasional Subcontracting
This is an alternative way of subcontracting operations.
Sometimes, when there are capacity problems, one of the operations for a certain manufacturing order is subcontracted and an external supplier performs the operation on this special order.
Outcome
An operation is rescheduled from in-house to be performed by an external supplier, and planned purchase order is created.
As part of this process, the following files are updated:
- MPOPLP Planning Proposal Purchase
- MPHEAD Purchase Order Header
- MPLINE Purchase Order Lines
- MGHEAD Stock Transaction, Header
- MGLINE Stock Transaction, Lines
- MPSURL Subcontracting Requisition Lines
Before You Start
- Settings in Define Basic Settings for Subcontracting must be fulfilled.
- Settings in Define Settings for Subcontracted Operations must be fulfilled.
Follow These Steps
These steps describe the scenario when a manufacturing order is placed on the end product and an operation shall now be rescheduled from in-house to be performed by an external supplier.
-
The product structure of the manufacturing order is changed in 'Manufacturing Order. Open Lines' (PMS101).
-
Delete the in-house operation (work center) and create a new operation with the sub contracted work center. Redisplay (PMS101/B).
-
When you press Close on the (PMS101/B) panel, 'Manufacturing Order. Reschedule' (PMS010/A) is started. Select option 'Create' and the rescheduling is initiated.
The rescheduling is carried out by an autojob.
-
Next step is to create the planned purchase order. Open 'Manufacturing Order. Open Lines' (PMS101) again. Open the G panel. Select F14= Crt sub contr. A planned purchase order can now be found in 'Planned Purchase Order. Open' (PPS170).
-
The rest of the subcontracted operation flow is the same as the normal flow, see Workflow for Subcontracted Operations.