Create Planned Manufacturing Order Manually
This document explains how you manually select the values and parameters that will control the planned manufacturing order that you created.
Outcome
You have created a planned manufacturing order that will be handled like other automatically created planned manufacturing orders.
These files are affected:
- stored in (All the planned manufacturing orders are MMOPLP)
- Information on load and capacity is taken from, and updated in, (MCPSPE), (MCPSUM) and (MWLOAD).
Manually creating a planned manufacturing order is a complement to the automatic creation of planned manufacturing orders. Planned manufacturing orders are dealt with by the planning function to later be released; that is, they are made accessible for the production function.
Before you start
Follow These Steps
-
Start 'Planned MO. Open' (PMS170).
-
On the B panel, press F17=Create, to create a planned manufacturing order.
-
On the A panel, fill in the 'Responsible', 'Warehouse' and 'Product no.' fields.
-
On the E panel, fill in these mandatory fields:
-
Finish date
Shift work is used in some fields of activity. In such cases, the time can also be specified. Shift work is planned in 'Facility. Open' (CRS008).
-
Planned quantity – change units if necessary.
Some products allow the unit option. See the settings in 'Item. Open' (MMS001).
-
Finish date
-
Check and correct the fields that are mandatory, but that include a previously determined value:
-
Responsible
Responsible is specified on the A panel. You can, however, also change the field from the E panel.
-
Order type
The order type controls how the order is to be handled in the order flow.
-
Structure type – occurs only for some products
Structure type is used to define more than one product structure per product and facility.
In 'Settings – Product Structure' (CRS787), define whether a structure type will exist for the product or not.
-
Responsible
-
Check and fill in, if necessary, the fields that are available, but not mandatory:
- Status - applies to the planned manufacturing order
- Status – applies to the manufacturing order
-
Project number
The field indicates the number of the work group to which the manufacturing order belongs.
-
Project element
The field indicates the manufacturing order's type of activity.
-
Schedule number
The field indicates the manufacturing order's schedule number in a planning group.
-
Production line
The field indicates the planning group in which the product will be produced.
-
Press Enter. The planned manufacturing order is now created.