Reclassify to Subcontract Manufacturing Order Operations
This instruction explains how you change an operation on a manufacturing order (MO) that was planned to be performed at a local work center to a subcontracted operation.
Outcome
The load has been reduced and one or several operations have been moved to an outside facility.
The following files are affected:
- MO operations file MWOOPE
- Detailed load for rough-cut capacity planning, stored in MCPSPE
- Capacity/load per resource and week, stored in MCPSUM
- Planning group workload per year, stored in MWLOAD
- MO header file MWOHED
- PO header file MPHEAD
- Purchase order line MPLINE
- PO address file MPPOAD
- Planning overview MITPLO.
Use subcontracted operations when there is a need for more capacity.
Before you start
There must be:
- An MO with a status between 20 and 80
- A work center for subcontracting orders. You define work centers in 'Work Center. Open' (PDS010).
Follow These Steps
-
Start 'Manufact Order. Open' (PMS100).
-
Select option 11=Material/operation to start 'Manufact Order. Open Lines' (PMS101/B3).
-
Double-click the operation you want to subcontract to display the G panel.
-
Replace the original work center with a subcontracted work center.
-
Select Next on the H, I and J panels, to get to 'MO Operation. Connect Operation Element' (PMS104/B).
-
Select Exit to return to 'Manufact Order. Open' (PMS100/B).
The order's status will have 2 as the second digit while the system is working. You can continue with the next step as soon as the second digit in the status is back to 0.
-
Select option 11=Material/operation to start 'Manufact Order. Open Lines' (PMS101/B3).
-
Double click the operation you want to subcontract to display the G panel.
-
Select F14=Create subcontracting operation to create a purchase order (PO) for the operation.
-
Press Enter to finish.