Change Operation Sequence Number
This procedure should be used to change the sequence of operations in a work order. This is carried out by changing the sequence number itself.
The result will be a new sequence number for an operation.
Before you start
Before the procedure can begin, the following prerequisite must be met:
- The operations must already exist in MOS101.
Follow these steps
The procedure can be initiated one of two ways.
- Select 'Work Order. Open' (MOS100). Highlight the work order that contains the operation to be deleted. Select option 'Materials and Operation' to display (MOS101).
- Select 'Work Schedule. Open Toolbox' (MOS195). Highlight the operation and select option 'Materials and Operations' to display (MOS101).
-
Highlight the operation to be changed and select option 'Change operation number'. Press Enter to confirm.
-
A new operation number must be entered. This number must not exist already. Press Enter to confirm.
-
Specify F3 to exit, (MOS010) will be displayed to allow rescheduling to take place.
-