Define Maintenance Agreement Line with Fixed Labor Cost
This document explains how you define an agreement line with a service for which the customer is charged a fixed price for labor, but pays for the actual material consumption.
Use this instruction when you wish to add a service job to a maintenance agreement.
Outcome
An agreement line with information about a service job covered by the agreement is defined.
The table with information about maintenance agreement lines, ACUAGL, is updated.
Use an agreement line with a fixed labor price when you do not know how much and what material is used in a service, but you do know how much time the service usually takes to perform. This allows you to set a fixed price on labor.
Before you start
A maintenance agreement header must be defined in 'Maint Agrmnt. Open' (COS410).
Follow these steps
- Start 'Maint Agrmnt. Open' (COS410/B).
- On the B panel, select the agreement for which you want to define an agreement line with a service and select option 11='Agreement lines' to display 'Maint Agrmnt. Open Lines' (COS411).
- Select panel sequence E F.
- On the B panel, specify service price method 5 and the start date for the agreement. Also specify the product, product structure and the service for which the agreement should be valid. If a blank agreement line is to be defined, ignore these fields. Select 'New record' to display the E panel.
- On the E panel, optionally, specify the maximum material price per item, transaction and order line. Also specify the warranty limits if applicable.
- Specify the maximum material cost allowed to charge the customer (optional). Press Enter to display the F panel.
- Limit zero pricing. Specify the limit in the material currency. Any material transactions below the limit have the sales price set to zero. You can connect a charge to the agreement line. The charge replaces the sales price for the transactions below the limit with one charge.
- On the F panel, specify if the material to be used in the service should be limited to material owned by the customer and if material expendables should be limited to customer owned material.
- If applicable, specify project elements. The project elements are added to order lines by default when an order is based on the agreement line.
- Press Enter to finish.