Create Budget from Resource Plan
This procedure is used to transfer resources in a resource plan to account entries (that is, budget transactions) for a budget. These entries are created from the cost components connected to each resource.
The account entries are then automatically transferred to a central budget. The greater value of planned quantity or adjusted quantity is used to calculate the costs.
Before you start
- A resource plan must be created. Refer to Create Resource Plan [Procedure].
- Costs per resource must be entered. This is done in ‘Budg Resource. Connect Cost Components’ (BUS016), which is reached by using option 11=‘Cost component’ in ‘Budget Resource. Open’ (BUS015).
- The resource plan that is to be converted to a budget must have general status 0=‘Not transferred to a budget’ and working status 0=‘Not blocked’.
Follow these steps
-
Start ‘Budget. Connect Budget Resource’ (BUS170/B).
-
Select option 9=‘Transfer’ for the resource plan to create a budget.
-
On the G panel, confirm the transfer by pressing Enter.