Scheduling Board modifications
Scheduling Board is a graphical representation of the schedule. If you require a more detailed information for each order or operation, use Schedule Report.
These are the panel modifications that you can do in Scheduling Board:
- Display text on the operation in the GANTT chart
- Display information in the box for the selected operation
Open the PMGANTT__.SKM panel file to modify the Scheduling Board.
Use the Panel #70 to control the information to display on the operations in the GANTT chart. If text mode is activated, the text displayed on the operation is for the selected operation or for all the operations. These are the information that you can modify:
- Order information
- Operation information
Use the Panel #79 to control the information to display in the box for the selected operation. These are the information that you can modify:
- Order information
- Derived order information
- Operation information
- Derived operation information
- Item register