Resource and calendar data

Resource and calendar data is used by M3 PWB to define a model of the production environment and to control finite capacity scheduling. The resource capacity model contains this data:
  • Work center resources
  • Work centers
  • Shift model days
  • Shift pattern lines
  • Non-working days
  • Transit time matrix
  • Setup time matrix
  • Capacity adjustments
  • Local parallel operations