Day bucket definitions locally
On the Buckets tab, specify this information:
- POT Table 1
- Leave this blank.
- Default start time
- Specify 10:30 or specify another start time.
- Default start weekday
- Select .
Example
This is an example if IPW is updated on 2027-01-27 at 09:25:
- The update timestamp is 2027-01-27 at 09:25.
- First Projected OHB column displays OHB is on 2027-01-26 at 10:30.
- Second Projected OHB column displays OHB is on 2027-01-27 at 10:30.
- Bucket starts on 2027-01-26 at 10:30 and ends on 2027-01-27 at 10:30.
- Bucket starts on 2027-01-27 at 10:30 and ends on 2027-01-28 at 10:30.
- First demand column displays demand between the bucket start on 2027-01-26 at 10:30 and the first bucket end on 2027-01-27 at 10:30.
- First supply column displays supply between two same date and time.
- The notice update timestamp is inside bucket 1.