Grid

The Grid is the primary part of the application where the planner can directly change the value of supplies and demands and can simulate the consequences of the applied changes.

The grid shows the projected on-hand balance or proj-OHB over a number of buckets. The balance for a specific date and time are displayed at the top of each proj-OHB columns. All demands and supplies for the specific dates and times are displayed between the proj-OHB columns. Each displayed cell in the grid has a tool tip that shows detailed information to calculate the value in the cell.

It is possible to select which columns to display in the grid in the Display tab under Settings. The user can add more columns per bucket or alternative not display supplies, demands, or proj-OHB.

  • Demand

    Demand is calculated as the sum of IPW Forecast, MO/MOP - material issue, DOP issue, Released DOs - issue, and other demand.

    IPW Forecast depends on these parameter settings:

    • If Manual Forecast (set in Settings/Miscellaneous) is activated and the value of Manual Forecast is greater than zero, and if Manual Forecast is not equal to forecast type, then the forecast for Inventory Planning Workbench is calculated as:
      Change + Max (Manual forecast - shipped CO, open CO)
    • If Forecast Method (set in Settings/Data Retrieval 1) is set as Consumed Forecast, then the forecast for Inventory Planning Workbench is calculated as:
      Remaining Forecast + open CO
    • If Forecast Method is set as Forecast, then the forecast for Inventory Planning Workbench is calculated as:
      Max(forecast - shipped CO, open CO)
    • If Forecast Method is set as None, then the forecast for Inventory Planning Workbench is Open CO.
      Note: The fields that are not used in calculating the FFP forecast are disabled in the tool-tip.
  • Supply

    Supply displays contributions from orders. The acquisition code controls which order is displayed in the supply cell:

    • 1: Manufactured considers supplies from manufacturing orders
    • 2: Purchased considers from purchase orders
    • 3: Distribution considers supplies from distribution orders
  • Projected on-hand balance

    Displays projected on-hand balance and calculates coverage time for the projected on-hand balance. Projected on-hand balance is calculated from the three previous cells, for example, previous projected on-hand balance, demand and supply for projected on-hand balance calculations.

    Projected on-hand balance for the first bucket is different. It is based on the approved on-hand balance and is adjusted for any outstanding demands and supplies.