Buckets
You can use this setting to control the start and end of grid buckets.
- Select .
- Specify this information:
- Number of buckets
- Select a value from the list. This setting is used to control the number of buckets that are displayed in the grid.
- POT warehouse
- Specify the warehouse where point of time is defined in RPS080.
- Always retrieve POT
- Select the check box to always retrieve POT, when is done in IPW. In production, do not select the check box as it reduces performance. The check box is relevant during testing or setup of IPW, where point of time continuously is changed and it is safer to always imported POT even if performance is affected.
- POT Table 1
- Specify the ID of point of time defined in RPS080.
- POTT 1 buckets
- Select the minimum number of POTT 1 buckets from the list.
- POT Table 2
- Specify the second ID of point of time defined in RPS080.
- Bucket offset
- Specify the number of buckets that is skipped when displaying information in the grid.
- Default start time
- Specify the default start time if point of time are not defined in RPS080.
- Default start weekday
- Select to specify that the default buckets are on a day level. Alternatively, select the day of the week each week starts on to specify that the default buckets are on a week level. You can only use this if point of time is not defined in RPS080.
- Exclude time part in buckets
- Select the check box to only display date as bucket ID in grid.
- Click .