Creating a new phantom

Follow these procedures to add a new phantom.
  1. Select Datasets > Phantoms.
  2. On Phantom Manager, click Add.
    A new phantom is created with the existing, new, or changed key values. The new phantom is listed above the original phantom and marked with status New.
  3. You can copy the data types for the new phantom if From / To Time Horizon and data types are selected for copy.
    If you created multiple new records, you can select the Data column check box to skip data copy for some of the records.
  4. Click OK.
  5. To verify the phantoms, select Datasets > Phantoms.

    The Phantoms dialog box is displayed with the new phantoms listed and marked with status Valid.

    Note:  You can use a blank budget if the dataset contains a blank budget and Total Forecasting is applied. When a new phantom is created, the AUMs are automatically deployed to the new cells.

    You must be logged on as an administrator to complete this task