Refreshing an issue summary

This procedure is applicable when your project activity contains an existing executive summary.
Note: The summary becomes outdated when the generated summary date is older than the issue header date. This situation occurs when the issue is updated, making the generated summary invalid.
  1. Click an issue from 'Issue. Open' (IMS100).

    If used in a workspace, click an issue from the M3 Information Viewer widget.

  2. On the Issue Overview widget, click Refresh summary for <issue number> where <issue number> depends on the selected issue for the display.