SCO Upstream Rescheduling Method (DO as mid-level)

Description

New logic for forward rescheduling of distribution orders for the supply chain order (SCO) upstream date change is introduced. Rescheduling, confirming, or put-away of the lowest level order (for example, manufacturing order or purchase order) in the supply chain triggers forward scheduling of the next higher level distribution order. This continues upwards until it reaches the top level demand order.

Limitations

The solution is limited only for supply chain order having Distribution Order in the middle of the chain. Manufacturing Order as mid-level order is not yet supported. No changes made for the upstream quantity change only for upstream date change.