Operation Time Analysis - Hours reports

The reports in Operation Time Analysis dashboard are filtered by MO Operation Status 90. Only operations that are flagged for completion and closed are displayed.

The measures used in Operation Time Analysis reports are sourced from the MO Operations fact. These measures are analyzed by Actual Finish Date and use the Sum aggregation. Some reports use Max, and Min aggregation.

Operation Punctuality in Hrs Overview

Description: This report shows an overview of operation punctuality in hours. The report shows the percentage of early, on time, and late finished operations.

Measure: No. of Operations

Chart type: 1 data series donut chart

Operation Punctuality in Hrs Breakdown by Period

Description: This report shows the operation punctuality breakdown of finished operations in hours at Year/Month level. The report shows the percentage of early, on time, and late finished operations over time.

Measure: No. of Operations

Chart type: 1 data series stacked 100% column chart

Partition: The Operation Punctuality – Hrs attribute is used as color to partition the chart.

Top Operations Finished Late in Hrs Pct

Description: This report shows the top work centers or products with operations finished late in hours percent.

Measure: Operations Finished Late Pct – Hrs

Chart type: 1 data series bar chart

Column selector: Work Center, Product Group, Item Group, Item

Bottom Operations Finished Late in Hrs Pct

Description: This report shows the bottom work centers or products with operations finished late in days percent.

Measure: Operations Finished Late Pct – Days

Chart type: 1 data series bar chart

Column selector: Work Center, Product Group, Item Group, Item

Avg Var in Hrs - Actual and Plnd Finish by Period

Description: This report shows the absolute value Avg Var in Hrs – Actual and Plnd Finish measure at Year/Month Level. Together with the average, maximum, and minimum, Hrs Var – Actual and Plnd Finish is also plotted in the chart in spline.

Measure:
  • Avg (abs): Avg Hrs Var – Actual and Plnd Finish
  • Max: Hrs Var – Actual and Plnd Finish
  • Min: Hrs Var – Actual and Plnd Finish

Chart type: 3 data series combo, 1 single column chart on Y axis 1 and 2 spline chart on Y axis 2

Top Avg Var in Hrs - Actual and Plnd Finish by Product

Description: This report shows the top Avg Var in Hrs – Actual and Plnd Finish measure by Product.

Measure: Avg (abs): Avg Hrs Var – Actual and Plnd Finish

Chart type: 1 data series bar chart

Column selector: Product Group, Item Group, Item

Bottom Avg Var in Hrs - Actual and Plnd Finish by Product

Description: This report shows the bottom Avg Var in Days – Actual and Plnd Finish measure by Product.

Measure: Avg (abs): Avg Days Var – Actual and Plnd Finish

Chart type: 1 data series bar chart

Column selector: Product Group, Item Group, Item

Avg Actual Duration in Hrs by Period

Description: This report shows the absolute value Avg Duration in Hrs – Actual measure at Year/Month Level. Together with the average, maximum, and minimum, Duration in Hrs – Actual is also plotted in the chart in spline.

Measure:
  • Avg: Avg Duration in Hrs – Actual
  • Max: Duration in Hrs – Actual
  • Min: Duration in Hrs – Actual

Chart type: 3 data series combo, 1 single column chart on Y axis 1 and 2 spline chart on Y axis 2

Duration in Hrs by Period

Description: This report shows the Duration in Hrs measures: Actual, Planned, and absolute value of Variance Pct at Year/Month Level. Side-by-side analysis of actual duration and planned duration together with the absolute value of variance percent measure can help give insight on whether the user is over-planning an operation.

Measure:
  • Actual: Duration in Hrs – Actual
  • Planned: Duration in Hrs – Plnd
  • Var Pct (abs)

Chart type: 3 data series combo, 2 grouped column chart on Y axis 1 and 1 spline chart on Y axis 2