WO Operations sourced measures and KPIs
This table shows the WO Operations measures that are sourced directly in Data Warehouse.
These measures can be analyzed by different time series. For the list of available time series measures, see Time.
Aggregations available are Avg, Max, Min, and Sum.
Measure | Description |
---|---|
Travel Hrs | The labor setup time in hours used to process the operation |
Labor Hrs | The labor run time in hours used to process the operation |
Total Hrs | The sum of actual travel and labor hours |
Plnd Travel Hrs | Number of man-hours required for travel to complete the operation |
Plnd Labor Hrs | Number of man-hours required to complete the operation |
Total Plnd Hrs | The sum of planned travel and labor hours |
Actual vs Plnd Travel Hrs Var | Actual travel hours minus the planned travel hours |
Actual vs Plnd Labor Hrs Var | Actual labor run hours minus the planned labor run hours |
Actual vs Plnd Total Hrs Var | Total labor hours minus the total planned labor hours |
No. of Operations | Number of work order operations |
Days Var – Actual and Plnd Start | Number of days between the actual start and planned start dates of the operation |
Hrs Var – Actual and Plnd Start | Number of hours between the actual start and planned start dates of the operation |
Days Var – Actual and Plnd Finish | Number of days between the actual finish and planned finish dates of the operation |
Hrs Var – Actual and Plnd Finish | Number of hours between the actual finish and planned finish dates of the operation |
Duration in Days – Actual | Number of days between the actual start and finish dates of the operation |
Duration in Hrs – Actual | Number of hours between the actual start and finish dates of the operation |
Duration in Days – Plnd | Number of days between the planned start and finish dates of the operation |
Duration in Hrs – Plnd | Number of hours between the planned start and finish dates of the operation |