Operation Time Analysis - Days reports
The reports in Operation Time Analysis dashboard are filtered by MO Operation Status 90. Only operations that are flagged for completion and closed are displayed.
The measures used in Operation Time Analysis reports are sourced from the MO Operations fact. These measures are analyzed by Actual Finish Date and use the Sum aggregation. Some reports use Sum, Max, and Min aggregation.
Operation Punctuality in Days Overview
Description: This report shows an overview of operation punctuality in days. The report shows the percentage of early, on time, and late finished operations.
Measure: No. of Operations
Chart type: 1 data series donut chart
Operation Punctuality in Days Breakdown by Period
Description: This report shows the operation punctuality breakdown of finished operations in days at Year/Month level. The report shows the percentage of early, on time, and late finished operations over time.
Measure: No. of Operations
Chart type: 1 data series stacked 100% column chart
Top Operations Finished Late in Days Pct
Description: This report shows the top work centers or products with operations finished late in days percent.
Measure: Operations Finished Late Pct – Days
Chart type: 1 data series bar chart
Column selector: Work Center, Product Group, Item Group, Item
Bottom Operations Finished Late in Days Pct
Description: This report shows the bottom work centers or products with operations finished late in days percent.
Measure: Operations Finished Late Pct – Days
Chart type: 1 data series bar chart
Column selector: Work Center, Product Group, Item Group, Item
Avg Var in Days - Actual and Plnd Finish by Period
Description: This report shows the absolute value Avg Var in Days – Actual and Plnd Finish measure at Year/Month Level. Together with the average, maximum, and minimum, Days Var – Actual and Plnd Finish is also plotted in the chart in spline.
- Avg (abs): Avg Days Var – Actual and Plnd Finish
- Max: Days Var – Actual and Plnd Finish
- Min: Days Var – Actual and Plnd Finish
Chart type: 3 data series combo, 1 single column chart on Y axis 1 and 2 spline chart on Y axis 2
Top Avg Var in Days - Actual and Plnd Finish by Product
Description: This report shows the top Avg Var in Days – Actual and Plnd Finish measure by product.
Measure: Avg (abs): Avg Days Var – Actual and Plnd Finish
Chart type: 1 data series bar chart
Column selector: Product Group, Item Group, Item
Bottom Avg Var in Days - Actual and Plnd Finish by Product
Description: This report shows the bottom Avg Var in Days – Actual and Plnd Finish measure by product.
Measure: Avg (abs): Avg Days Var – Actual and Plnd Finish
Chart type: 1 data series bar chart
Column selector: Product Group, Item Group, Item
Avg Actual Duration in Days by Period
Description: This report shows the absolute value Avg Duration in Days – Actual measure at Year/Month Level. Together with the average, maximum, and minimum, Duration in Days – Actual is also plotted in the chart in spline.
- Avg: Avg Duration in Days – Actual
- Max: Duration in Days – Actual
- Min: Duration in Days – Actual
Chart type: 3 data series combo, 1 single column chart on Y axis 1 and 2 spline chart on Y axis 2
Duration in Days by Period
Description: This report shows the Duration in Days measures: Actual, Planned, and absolute value of Variance Pct at Year/Month Level. Side-by-side analysis of actual duration and planned duration together with the absolute value of variance percent measure can help give insight on whether the user is over-planning an operation.
- Actual: Duration in Days – Actual
- Planned: Duration in Days – Plnd
- Var Pct (abs)
Chart type: 3 data series combo: 2 grouped column chart on Y axis 1 and 1 spline chart on Y axis 2