Labor Resource Analysis calculated measures and KPIs
This table shows the Labor Resource Analysis measures that are calculated and defined as saved expressions.
The expressions are based on sum aggregation.
Measure | Description |
---|---|
Actual vs Plnd Hrs Var – Labor Pct | The variance between actual and planned labor hours divided by the planned labor hours |
Actual vs Plnd Hrs Var – Travel Pct | The variance between actual and planned travel hours divided by the planned travel hours |
Cap vs Actual Hrs Var | The work center capacity minus the actual labor hours |
Cap vs Actual Hrs Var Pct | The variance between the work center capacity and labor hours divided by the work center capacity |
Cap vs Plnd Hrs Var | The work center capacity minus the planned labor hours |
Cap vs Plnd Hrs Var Pct | The variance between the work center capacity and planned hours divided by the work center capacity |
Disturbance Hrs Pct | The disturbance time in hours divided by the total labor hours |
Labor Hrs Pct | The actual labor hours divided by the total labor hours |
Labor vs Total Actual Hrs Pct | The actual labor hours divided by the total actual hours |
Stop Hrs Pct | The stop time in hours divided by the total labor hours |
Total Actual vs Plnd Hrs Var Pct | The variance between the total actual and planned hours divided by the total planned hours |
Travel Hrs Pct | The actual travel time divided by the total labor hours |
Travel vs Total Actual Hrs Pct | The actual travel hours divided by the total actual hours |
Utilization Pct | The total actual hours divided by the work center capacity |