Work Center Utilization calculated measures and KPIs
This table shows the Work Center Utilization measures that are calculated and defined as saved expressions.
The expressions are based on sum aggregation.
Measure | Description |
---|---|
Avg Order Qty | Order quantity divided by the number of finished manufacturing orders |
Avg Setup Hrs per MO | Total setup hours of the work center divided by the number of finished manufacturing orders |
Efficiency Pct | Ratio between planned and actual hours multiplied by the ratio between manufactured and ordered quantity |
Maint vs Total Down Time Pct | Actual maintenance hours divided by the sum of maintenance and disturbance hours |
Mfd vs Order Qty Var Pct | The difference between manufactured quantity and ordered quantity divided by the ordered quantity |
Stop Time vs Maint Hrs Pct | Stop time reported divided by the maintenance hours |
Utilization Pct | Total actual time of work center divided by the total capacity in hours |
Work Ctr Throughput per Hour | Manufactured quantity divided by the work center's run time |