Creating Subcontractor Purchase Orders
Creating and processing subcontract purchase orders is similar to creating and processing other purchase orders, with the following exceptions:
-
Because you are subcontracting for services, not products or materials, you create subcontract purchase orders only on Purchase Order Entry (PO20.1). Requisitions cannot create subcontractor purchase orders.
-
Each line on a subcontractor purchase order must contain activities associated with a single PI, because PI is the trigger for approval through Infor Process Automation
-
Vendors indicated on a subcontract purchase order are checked to be sure they are valid subcontractors for the grant award(s) on the purchase order.
-
After a subcontract purchase order is released, the status displays as "needs approval." Once the records are ready for approval, they can be approved through Infor Process Automation, or on Purchase Order Direct Approval (PO24.1).
Before you can process any subcontractor purchase orders, the following setup must be complete:
- The subcontractor must be defined as a vendor on Vendor (AP10.1)
- The Award field on Activity (AC10.1) must be set to Yes for the posting activity.
- The award must be defined in Grant Management with the Principal Investigator (PI) defined on Award Personnel (GM03.1), and the subcontractor vendor set up on Award Subcontractors (GM03.2)
To create subcontractor purchase orders