Running the document integrity check
In Phase Two, you run the document integrity check programs to check closed headers and detail lines to make sure that the detail lines of each record correspond to its header information. Also, the Phase Two programs ensure that any open lines have an open header and a corresponding demand record within these applications:
-
Requisitions
-
Order Entry
-
Production Order
-
Purchase Order
-
Warehouse
If header records are out of sync, then running these programs creates missing demand and demand header records, as necessary.
Note: Most problems that are discovered by running the Phase
Two programs can be automatically repaired. With the others, you must
manually repair the problems because the Phase Two program does not
know how to best resolve the problems for your specific business.