Usage

Use the milestone billing method for fixed price contracts that specify when billing can occur. The customer is billed when a milestone is reached or completed.

Percent Complete Milestones

You can bill based on the percentage of completion. The percentage of completion is calculated based on the type of budget:

For an amount budget: % Complete = Activity cost amounts / total budgeted
For a unit budget: % Complete = Activity cost units / total budgeted

Milestone Status

The milestone status indicates whether the milestone is ready to be billed, has been billed, is open, or is on hold.

You can define the following milestone status types:

Status Description
(1) To Process The milestone is to be included in the next billing calculation.
(2) Processed The milestone has been billed.
(3) Hold The milestone is on hold from billing.