Calculating percentage of completion
Use this procedure to calculate percentage complete for activity groups, activities, and account categories. This lets you measure activity progress by calculating the percentage of budget completed to date. Percent complete is calculated as: Percent Complete = Cost to Date / Life to Date Budget.
Related reports and inquiries
Function | Form |
---|---|
Perform an online analysis of the percentage complete for activities and account categories. | Activity Percentage of Completion (AC65.1) |
Report on percentage of completion for activities or account categories. | Percent Complete Report (AC265) |