Re-exploding work orders
After you have exploded a work order, you can re-explode it if you need to make
- 
           
changes to finished good quantities and you want the components to explode in proportion to the new finished good quantity,
 - 
           
changes to the finished good itself (such as component quantity, burdens, and so on) using Finished Goods (IC62.1),
 - 
           
reverse changes to the components, burdens, and byproducts on an exploded work order, and
 - 
           
changes that affect the inventory cost of producing the finished good, and the burden type is a percentage of inventory cost. You must re-explode the work order to recalculate planned burden cost.