Approving Subcontractor Purchase Orders
The two ways to approve a subcontractor purchase order are to:
-
Complete the Infor Process Automation approval process (see the LPA Services for Infor Lawson Reference Guide).
-
Directly approve using Purchase Order Direct Approval (PO24.1).
A Principal Investigator (PI) can unrelease, approve, or reject the subcontractor purchase order (the current status displays on PO24.1). After a subcontractor purchase order is approved, making changes to details like quantities, activities, or cost cause the subcontractor purchase order to be unreleased. When you release it a second time, you start the approval process again.
To approve a subcontractor purchase order
- Access Purchase Order Direct Approval (PO24.1).
- Select the company, vendor, purchase from, and PO number.
- Select the Approve form action.
Related Reports and Inquiries
To | Use |
---|---|
Monitor subcontractor purchase orders by status (the report sorts by vendor) | Subcontractor Monitoring Report (PO240) |