Changing Activity Status
An activity status is a user-defined function which allows you to perform specific actions associated with the activity. Status code functions which can be assigned to activities are posting, budgeting, cost allocation, revenue recognition, billing, capitalization, and purging records. Be sure the activities for which you want to calculate revenue have been assigned a status that includes revenue recognition.
This procedure describes how to change the status of an activity.
Note: This procedure assumes a prior knowledge of the Project Accounting application.
For detailed procedures, see the Project Accounting User Guide.
Before you can change the status of an activity, you must define a status code on Status (AC02.1) and assign a status to an activity on Activity (AC10.1).
To change activity status
Related Reports and Inquiries
To | Use |
---|---|
View a listing of Statuses | Status Listing (AC202) |
View a listing of Activities based on status | Activity Listing (AC210) |