Changing the status of an activity
Use this procedure to change the status of individual activities or a group of activities. For example, you can change the status of a group of activities to make them eligible for purging.
- Access Mass Activity Status Change (AC112).
- On the Activity tab, specify this information:
- Activity Group List, Activity Group, Activities, or Activity List
-
Select one of these options:
-
An activity group list to do a mass status change for the specified activity group list.
-
An activity group to do a mass status change for the specified activity group.
-
Up to six activities for which the mass status change can apply.
-
A predefined list of activities for which the mass status change can apply.
-
- Include Lower Levels
-
Select whether to update all activities under any summary or contract activities you select. If you select No (N), then AC112 cannot automatically update the activities under the activities you specified in the Activities or Activity List fields.
Note: This option applies only if you select activities or an activity list. AC112 always updates all activities within an activity group. - New Status
-
Select the new status to assign to the selected activities.
- Update
-
Select whether to update the file and get a listing of the changes (Yes) or just get an edit listing of the mass status changes that can take place when the program is run to update (No).
- On the Other Options tab, specify this information:
- Last Posted Date
-
You can use the Last Posted Date to select activities for the mass status change based on their last transaction posting date. For example, you might assign a purge status to all activities that were not posted in the last two years.
- Beginning Date
-
To select activities in a date range for the mass status change, specify the beginning and end date of the range. This date range corresponds to the activity date range defined in Activity (AC10.1). If an activity's date range falls within the range you specify in this field, then that activity is included in the status change.
- End Date
-
To select activities in a date range for the mass status change, specify the beginning and end date of the range. This date range corresponds to the activity date range defined in Activity (AC10.1). If an activity's date range falls within the range you specify in this field, then that activity is included in the status change.