Activity Percentage of Completion (AC65.1)

Use Activity Percentage of Completion (AC65.1) to calculate percent complete for activities. This lets you measure activity progress by viewing the percentage of budget completed to date.

Percent complete is calculated as follows: Percent Complete = Cost to Date / Life to Date Budget. You can calculate percentage of completion using Percent Complete Calculation (AC165) or you can use the Load function to have the system calculate it on AC65.1 and AC65.2.

Use AC65.1 or AC65.2 to compute percent complete online, or use AC165 to perform a batch calculation. Using AC65.1 or AC65.2, you can edit the computed percent complete if necessary, while you do not have that opportunity using AC165.