Resource Interface (AC520)
Run Resource Interface (AC520) to import resource information from a non-Lawson system to Project Accounting.
You can import resources when adding new activities, or you can import resources for existing activities. Resources can be assigned to an activity or an activity group. AC520 and Activity Interface (AC500) can be run at different times. Use Resource Interface Adjustment (AC52.1) to edit resource records.
Processing effect
For UNIX/Windows platforms: The data is stored in the ACIFRESC (Activity Resource Import) file. When you run AC520 (Resource Import), it updates the ACRESOURCE (Activity Resource) and the ACASSIGN (Activity Resource Assignment) files.
For the IBM i platform: The data is stored in the DBACAFR (Activity Resource Import) file. When you run AC520 (Resource Import), it updates the DBACRSC (Activity Resource) and the DBACAAN (Activity Resource Assignment) files.