Program Metrics
This widget displays the data related to budget variance, contract profitability and schedule adherence.
- Budget Variance: This KPI displays the difference between the estimate at completion at the end of the project and Budget planned for the project.
Formula:
This value is applicable to the selected program and aggregated for all the projects that are associated with the program.Budget Variance= Estimate at Completion (EAC) - Budget at Completion (BAC)/ Budget at Completion (BAC)% - Net Contract Profitability: This KPI displays the current profit made from the contracts.
Formula:
This value is applicable to the selected program and aggregated for all the projects that are associated with the program.Net Contract Profitability= Revenues Recognized till date - Cost of Sales till date/ Cost of Sales till date% - Schedule Adherence: This KPI provides insight on the timeliness of the activities of the projects.
Formula:
Schedule Adherence= OTP (on Time Performance) = No. of activities completed till date/ No. of activities planned to be completed as on date