Program Performance
This widget displays all the KPIs and amount associated with project in a program, including the details such as earned value, actual cost, budget amount, and EAC.
The displayed data is based on the type of KPIs selected. There are two different KPIs:
- Indices: This KPI displays budget amount, actual costs, EAC, completion date, CPI, SPI,VAC% and OTP for the project. For CPI, SPI and OTP, the calculated value is displayed:
- In Green if greater than or equal to 1.
- In Yellow if within to 0.95 to 0.99.
- In Red if less the 0.95.
- The KPI calculates the CPI, SPI, VAC and OTP using these formulae:
-
- CPI:
Earned Value/Actual Cost - SPI:
Earned Value/Total Budget - VAC%:
Estimate at Completion (EAC) - Budget at Completion (BAC)/ Budget at Completion (BAC). The value is displayed in the green color if VAC is greater than 0; the value is displayed in yellow color if the VAC is equal to -5 to 0.009 and the value displayed in red color if the VAC is less the -5. - OTP:
No. of activities completed till date/ No. of activities planned to be completed as on date
- CPI:
-
- Amount: This KPI displays budget amount, actual costs and EAC for the project.