Apportioned (hours)

Apportioned efforts' intrinsic performance is related to other discrete activity. The release of the budget amount is the same as that for the discrete activity.

  • Planned Value

    The release of the budget amount is the same as that for the discrete activity. Hours are derived from the activity while the schedule dates are derived from the discrete activity.

  • Earned Value

    The calculation of the Earned value is the same as that for the discrete activity. Hours are derived from the activity while the actual dates and progress are derived from the discrete activity.

Example:

  • If the Earned Value Method (EVM) of the discrete activity is Percent Complete, see ‘Percent Complete’ example.
  • If the Earned Value Method (EVM) of the discrete activity is Start and End Percentage, see ‘Start and End Percentage’ example.
  • If the Earned Value Method (EVM) of the discrete activity is Milestone, see ‘Milestone’ example.
  • If the Earned Value Method (EVM) of the discrete activity is Level of Effort, see ‘Level of Effort’ example.