Others
This folder contains measures using calculations from different facts.
Measure | Description |
---|---|
Activity Count | Count of activities |
CPI | Cost Performance Indicator = Earned Value /Actual Cost |
Currency | Based on the selected Currency Type filter, the currency is
retrieved as follows: Data warehouse Currency of the Financial Company linked – tcgen000.dcur Local Currency of the Financial Company linked – tcemm170.fcua Reference Company of the Financial Company linked – tcemm170.lcur Reporting Currency 1 of the Financial Company linked – tcemm170.fcub Reporting Currency 2 of the Financial Company linked – tcemm170.fcub Project Currency – tppdm600.ccur Contract Currency - tpctm100.ccur Transaction Currency – currency from the transaction |
Effort | (Earned Hours – Actual Hours) / Earned Hours |
On Budget | If Actual Cost <= Budget, then on budget. Else, beyond budget. |
On Time | If Activity schedule finish <= Baseline activity finish date, then on time. Else, delayed. |
OTP | Number of activities completed till date / Planned to complete till date |
Project Count | If valid project, then 1. Else, 0. |
SPI | Schedule performance indicator = Earned Value / Budget |
TCPI | Budget – Earned Value / Estimate at Completion – Actual |
Time Unit | tcmcs000.ctim |
VAC | BAC – Estimate at completion |
Work in Progress | Actual cost when reported complete tpppc200.comf is <> yes |