Project Earned Value Measures
Project Earned Value shows the active Earned Value based on active bottom up time phased budget. It must be used while analyzing or monitoring a project by actual Budget\ Cost\ Revenue\ Forecast etc. Measures are configured by latest approved baseline, active plan and active budget analysis code.
This table shows the measures that are mapped to LN table fields or calculated:
Measure | Mapping | Note |
---|---|---|
CPI | Earned Value / Actual Cost | |
Cost Variance | Earned Value – Actual Cost | |
Cumulative Cost Variance | Cumulative Cost Variance by Period | Non-Additive Measure |
Cumulative Earned Hours | Cumulative Earned Hours by period | Non-Additive Measure |
Cumulative Earned Quantity | Cumulative Earned Quantity by period | Non-Additive Measure |
Cumulative Earned Value | Cumulative Earned Values by period | Non-Additive Measure |
Cumulative Schedule Variance | Cumulative Schedule Variance by Period | Non-Additive Measure |
Earned Hours | Earned Value quantity in time unit (only for labor budgets) | |
Earned Quantity | Earned Value quantity in transaction unit | |
Earned Value | Calculated based on EV method defined on the activity | |
SPI | Earned Value / Budget | |
Schedule Variance | Earned Value – Budget | |
Project Earned Value Count | Calculated in Birst ETL |