Project Bottom up Budget Measures
Project Bottom Up Budget Measures are the active bottom up time phased budgets by period which must be used while analyzing or monitoring project by Budget\Cost\Revenue\Forecast etc. For activity-based budgets, measures are configured by latest approved baseline, active plan and active budget analysis code. For element-based budgets, measures are configured by active budget analysis code.
Measure | Mapping | Note |
---|---|---|
BAC | Budget at Completion | |
Balance Budget | Remaining Budget (Budget – Actual Costs) | |
Balance Budget Percentage | (Budget – Actual Costs)/Budget % | |
Balance Budgeted Hours | Budget hours – Actual Hours | |
Balance Budgeted hours Percentage | (Budget hours – Actual Hours)/Budget Hours % | |
Balance Budgeted Quantity | Budgeted Quantity – Actual Quantity | |
Budget | Budget amount tpptc311.amoc | |
Budget RFC | Budget amount in reference currency | |
Budget till Current Period | Budget amount tpptc311.amoc till current period | |
Budgeted Hours | Budget quantity in time unit (only for labor budgets) tpptc311.quan_base_time | |
Budgeted Quantity | Budget quantity in transaction unit tpptc311.quan | |
Cumulative Balance Budget | Cumulative balance Budget amount tpptc311.amoc till current period | Non-Additive Measure |
Cumulative Balance Budgeted Hours | Cumulative balance Budget hours tpptc311.quan by period | Non-Additive Measure |
Cumulative Balance Budgeted Quantity | Cumulative Budgeted Quantity tpptc311.quan by period | Non-Additive Measure |
Cumulative Budget | Cumulative Budget amount tpptc311.amoc by period | Non-Additive Measure |
Cumulative Budgeted hours | Cumulative Budgeted hours tpptc311.quan by period | Non-Additive Measure |
Cumulative Budgeted Quantity | Cumulative Budgeted hours tpptc311.quan by period | Non-Additive Measure |
Project Bottom Up Budget Count | Fact count sourced from tpptc311 |