Posting Type of Costs

Posting Types are used to identify financial transactions and to determine how the transactions must be posted to the general ledger.

Posting types indicate where the financial transaction originates from and combine related posting types in the project cost and revenue history. Infor LN sends the posting type as Actual cost, Hard Commitment, or Soft Commitment in the Project Cost messages for each cost transaction.

Published Value in IMS LN Value Description Type of Cost
tpppc.ptyc.add.calc.offvar Additional Calculation Office Variance Additional calculation office variance Actual Cost
tpppc.ptyc.contract Contract Contract Actual Cost
tpppc.ptyc.adjustment Adjustment Adjustment Actual Cost
tpppc.ptyc.cogs.price.var COGS Price Variance Actual Cost
tpppc.ptyc.work.ord.pr.var Work Order Price Variance Work order price variance Actual Cost
tpppc.ptyc.dir.del.iss Direct Delivery Issue Actual Cost
tpppc.ptyc.dir.del.iss.inv Direct Delivery Issue Intercompany Actual Cost
tpppc.ptyc.dir.del.var Direct Delivery Variance Actual Cost
tpppc.ptyc.direct.delivery Direct Delivery Actual Cost
tpppc.ptyc.issue.result Issue Result Issue result Actual Cost
tpppc.ptyc.expenses Expenses Costs entered as employee expenses related to a project Actual Cost
tpppc.ptyc.var.adjustment Variance Adjustment Actual Cost
tpppc.ptyc.freight.pr.var Freight Price Variance Actual Cost
tpppc.ptyc.field.ch.order Field Change Order Costs Actual Cost
tpppc.ptyc.freig.cost Freight Costs Actual Cost
tpppc.ptyc.gen.costs.var General Costs Variance General costs variance Actual Cost
tpppc.ptyc.general.fin General Costs (through Financials) General costs (through Financials) Actual Cost
tpppc.ptyc.general General Costs General costs Actual Cost
tpppc.ptyc.gen.costs.wo General Costs Work Order Actual Cost
tpppc.ptyc.interim.result Interim Result Interim Results
tpppc.ptyc.issue Issue Issue Actual Cost
tpppc.ptyc.issue.invoiced Issue Intercompany Actual Cost
tpppc.ptyc.item.surch.rec Item Surcharge Receipt Item surcharge receipt Actual Cost
tpppc.ptyc.item.surch.iss Item Surcharge Issue Item surcharge issue Actual Cost
tpppc.ptyc.on.order On Order Commitment originating from purchase order entry Soft Commitment
tpppc.ptyc.operation Operation Costs Actual Cost
tpppc.ptyc.price.variance Price Variance Costs originating from a purchase price variance Hard Commitment
tpppc.ptyc.trans.serv.wip Transfer from Service WIP Actual Cost
tpppc.ptyc.quarantine.rec Quarantine Receipt Actual Cost
tpppc.ptyc.pur.price.var Purchase Price Variance Actual Cost
tpppc.ptyc.receipt Receipt Commitment originating from assigning a purchase order to a project Hard Commitment
tpppc.ptyc.rejection Rejection Hard Commitment
tpppc.ptyc.revenues Revenues Actual Cost
tpppc.ptyc.revenues.anal Revenues Analysis Actual Cost
tpppc.ptyc.rev.interim.res Reverse Interim Result Reverse Interim Results
tpppc.ptyc.receip.invoiced Receipt Intercompany Actual Cost
tpppc.ptyc.shipment.var Shipment Variance Costs originating from a shipment variance Actual Cost
tpppc.ptyc.subcontracting Subcontracting Actual Cost
tpppc.ptyc.subcontr.wip Subcontracting WIP Actual Cost
tpppc.ptyc.reject.invoiced Rejection Intercompany
tpppc.ptyc.subcontr.inv Subcontracting Invoiced Actual Cost
tpppc.ptyc.operation.inv Operation Costs Intercompany Actual Cost
tpppc.ptyc.gen.cost.wo.inv General Costs Work Order Intercompany Actual Cost
tpppc.ptyc.ship.var.inv.pr Shipment Variance Intercompany (Project) Actual Cost
tpppc.ptyc.gen.costs.inv General Costs Intercompany Actual Cost
tpppc.ptyc.material Material Actual Cost
tpppc.ptyc.mat.invoiced Material Intercompany Actual Cost
tpppc.ptyc.value.correct Value Correction Value correction Actual Cost
tpppc.ptyc.repair.warranty Repair Warranty Costs Repair warranty costs Actual Cost
tpppc.ptyc.wip.hours WIP Hours Work in process hours Actual Cost
tpppc.ptyc.warranty.costs Warranty Costs Warranty costs Actual Cost
tpppc.ptyc.wip.cst.finance WIP Costs (through Financials) Actual Cost
tpppc.ptyc.wip.tran.issue WIP Transfer Issue Actual Cost
tpppc.ptyc.wip.tran.receip WIP Transfer Receipt Actual Cost
tpppc.ptyc.wip.tran.recinv WIP Transfer Receipt Intercompany Actual Cost
tpppc.ptyc.warh.surch.iss Warehouse Surcharge Issue Warehouse surcharge issue Actual Cost
tpppc.ptyc.warh.surch.rec Warehouse Surcharge Receipt Warehouse surcharge receipt Actual Cost
tpppc.ptyc.cogs Cost Of Goods Sold Actual Cost
tpppc.ptyc.goodwill Goodwill Goodwill Actual Cost
tpppc.ptyc.tool.costs Tool Costs Tool costs Actual Cost
tpppc.ptyc.tool.costs.inv Tool Costs Intercompany Actual Cost
tpppc.ptyc.issue.inv.proj Issue Intercompany (Project) Actual Cost
tpppc.ptyc.ln.cost Landed Costs Landed costs Actual Cost
tpppc.ptyc.ln.cost.var Landed Costs Variance Landed costs variance Hard Commitment
tpppc.ptyc.ln.cost.inv Landed Costs Invoiced Landed costs invoiced Hard Commitment
tpppc.ptyc.ln.cost.inv.var Landed Costs Variance Invoiced Landed costs variance invoiced Actual Cost
tpppc.ptyc.invoiced.wip Invoiced WIP Invoiced work in process Actual Cost
tpppc.ptyc.issue.proj Issue (Project) Actual Cost
tpppc.ptyc.loan.result Loan Result Loan result Actual Cost
tpppc.ptyc.so.price.var Sales Order Price Variance Actual Cost
tpppc.ptyc.cogs.int.inv COGS Intercompany Actual Cost
tpppc.ptyc.plan.st.paym Planned Stage Payment Soft Commitment
tpppc.ptyc.rel.st.paym Released Stage Payment Hard Commitment
tpppc.ptyc.rel.st.paym Receipt (Stage Payment) Hard Commitment
tpppc.ptyc.loan Loan Monitoring
tpppc.ptyc.borrow Borrow Monitoring
tpppc.ptyc.payback.result Payback Result Actual Cost
tpppc.ptyc.rec.var.st.paym Receipt Variance (Stage Payment) Project WIP
tpppc.ptyc.cost.peg.trf.sp Cost Peg Reallocation (Stage Payment) Actual Cost
tpppc.ptyc.curr.var.sp Currency Variance (Stage Payment) Actual Cost
tpppc.ptyc.approval Approval (Claim)
tpppc.ptyc.exp.tax.st.paym Expense Tax (Stage Payment) Actual Cost
tpppc.ptyc.loan.reversal Loan Reversal Monitoring
tpppc.ptyc.borrow.reversal Borrow Reversal Monitoring
tpppc.ptyc.curr.var Currency Variance Actual Cost
tpppc.ptyc.wip.quar.iss WIP Quarantine Issue Actual Cost
tpppc.ptyc.quarantine.adj Quarantine Adjustment Actual Cost
tpppc.ptyc.curr.var.lc Currency Variance (Landed Costs) Actual Cost
tpppc.ptyc.rev.interc Revenues Intercompany
tpppc.ptyc.wip.costs.ic WIP Costs Intercompany
tpppc.ptyc.wip.hours.ic WIP Hours Intercompany
tpppc.ptyc.expenses.ic Expenses Intercompany
tpppc.ptyc.ln.cost.ic Landed Costs Intercompany
tpppc.ptyc.ln.cost.inv.ic Landed Costs Invoiced Intercompany
tpppc.ptyc.rec.ic.st.paym Receipt Intercompany (Stage Payment)
tpppc.ptyc.dir.rec.ic Direct Receipt Intercompany
tpppc.ptyc.variance.ic Variance Intercompany
tpppc.ptyc.cogs.variance COGS Variance
tpppc.ptyc.cos.rec Cost of Sales Recognition
tpppc.ptyc.cmt.soft.pc Soft Commitment (Project Control) Manually entered commitments Soft Commitment
tpppc.ptyc.cmt.soft.pc.rev Soft Commitment (Project Control) – Rev Manual reversal of previously entered soft commitments, after posting to general ledger Soft Commitment
tpppc.ptyc.receipt.prj.wrh Receipt (Project Warehouse) Commitment originating from delivery of the ordered items to the project warehouse Hard Commitment
tpppc.ptyc.matched.receipt Matched Receipt Reversal of the hard commitment when a purchase invoice is processed Hard Commitment
tpppc.ptyc.project.control Project Control Manually entered project costs Actual Cost
tpppc.ptyc.inventory Inventory Material costs originating from a planned warehouse transfer Actual Cost
tpppc.ptyc.cost.invoice Cost Invoice Costs originating from a purchase cost invoice Actual Cost
tpppc.ptyc.price.var.rev Price Variance – Rev Reversal of costs created for a purchase price variance Hard Commitment
tpppc.ptyc.expense.tax Expense Tax Purchase costs originating from non-deductible tax Actual Cost
tpppc.ptyc.ln.cost.exp.tax Landed Costs Expense Tax Landed costs expense tax Actual Cost
tpppc.ptyc.pur.invoice Purchase Invoice Costs originating from a purchase order related invoice Actual Cost
tpppc.ptyc.ln.cost.wo.invc Landed Costs without Invoice Additional costs for which no purchase invoice is received Actual Cost
tpppc.ptyc.field.service Field Service Cost Costs that originate from a service order Actual Cost
tpppc.ptyc.labor Labor Cost Costs for time-registered hours Actual Cost
tpppc.ptyc.hours.subcontr Hours (Subcontracting) Costs originating from subcontracting labor Actual Cost
tpppc.ptyc.manual.sales Manual Sales Sales value originating from a manually entered billable cost line Actual Cost
tpppc.ptyc.charge.soft.cmt Surcharge on Soft Commitment Surcharges on soft commitments Soft Commitment
tpppc.ptyc.charge.hard.cmt Surcharge on Hard Commitment (Project) Surcharges on hard commitments Hard Commitment
tpppc.ptyc.charge.cost Surcharge on Cost Surcharges on costs Actual Cost
tpppc.ptyc.applied.ovhd Applied Overhead Recognized overhead costs Actual Cost
tpppc.ptyc.stage.invoice Stage Payment Invoice Stage Payment Invoice Actual Cost
tpppc.ptyc.cost.peg.trf.ex Cost Peg Reallocation (Expense Tax) Payback Variance Actual Cost
tpppc.ptyc.curr.gain.loss Currency Gain and Loss Actual Cost