Project Bottom up Budget Version Measures
Project Bottom Up Budget Version measures are the versions of bottom up time phased budgets by period. These measures must be used when comparing different versions of Bottom Up Budget. You must select Project Baseline and Project Bottom Up Budget Version in that case.
Measure | Mapping | Note |
---|---|---|
BAC | Budget at Completion | |
Balance Budget | Remaining Budget (Budget – Actual Costs) | |
Balance Budget Percentage | (Budget – Actual Costs)/Budget % | |
Balance Budgeted hours | Budget hours – Actual Hours | |
Balance Budgeted hours Percentage | (Budget hours – Actual Hours)/Budget Hours % | |
Balance Budgeted Quantity | Budgeted Quantity – Actual Quantity | |
Budget | Budget amount tpptc311.amoc | |
Budget till Current Period | Budget amount tpptc311.amoc till current period | |
Budgeted Hours | Budget quantity in time unit (only for labor budgets) tpptc311.quan_base_time | |
Budgeted Quantity | Budget quantity in transaction unit tpptc311.quan | |
Cumulative Balance Budget | Cumulative balance Budget amount tpptc311.amoc till current period | Non-Additive Measure |
Cumulative Balance Budgeted Quantity | Cumulative balance Budget amount tpptc311.quan till current period | Non-Additive Measure |
Cumulative Balance Budgeted hours | Cumulative balance Budget hours tpptc311.quan by period | Non-Additive Measure |
Cumulative Budget | Cumulative Budget amount tpptc311.amoc by period | Non-Additive Measure |
Cumulative Budgeted hours | Cumulative Budgeted hours tpptc311.quan by period | Non-Additive Measure |
Cumulative Budgeted Quantity | Cumulative Budgeted hours tpptc311.quan by period | Non-Additive Measure |
deleted | 1 if deleted in LN, else 0 |