Measures

This table shows the production order measures:

Measure Mapping Note
Active 1 if order status is Active, else 0
Actual Production Time Hours Actual Delivery Date – Actual Production Start Date

0 if negative

0 if not delivered or not started

Actual Throughput Duration Actual Delivery Date – Actual Production Start Date

0 if negative

0 if not delivered or not started

(1)
Bad Quantity Quantity Scrapped + Quantity Rejected + Quantity Quarantined
Closed 1 if order status is Closed, else 0
Completed 1 if order status is Completed, else 0
Delivered Early Days Requested Delivery Date - Actual Delivery Date

0 if negative

(1)
Delivered Late Days Actual Delivery Date - Requested Delivery Date

0 if negative

(1)
Early 1 if Actual Delivery Date is before Requested Delivery Date

0 if Actual Delivery Date is on or after Requested Delivery Date

0 if not delivered (no Actual Delivery Date)

Item Count Distinct Distinct item count
Late 1 if Actual Delivery Date is after Requested Delivery Date

0 if Actual Delivery Date is before or on Requested Delivery Date

0 if not delivered (no Actual Delivery Date)

On Time 1 if not Early and not Late. Else, 0.
Overrun Actual Throughput Duration - Planned Throughput Duration

0 if Actual Throughput Duration is less than Planned Throughput Duration

Overrun Ratio Overrun / Planned Throughput Duration

0 if Planned Throughput Duration is 0

PCS Project Count Distinct Distinct PCS project count
Perfect Order 1 if not late and no shortage (Late = 0 and Shortage = 0)

0 if late or shortage

Perfect Order Ratio Perfect Order / Production Order Count
Planned Production Time Hr Planned Delivery Date – Production Start Date and Time

0 if negative

Planned Throughput Duration Requested Delivery Date – Production Start Date and Time

0 if negative

(1)
Production Completed 1 if order status is Production Completed, else 0
Production Order Count Always 1 but 0 for null records
Quantity Backflushed tisfc001.qbfd
Quantity Delivered tisfc001.qdlv
Quantity Initial tisfc001.qntl
Quantity Negative Variance -1 * Quantity Variance if negative, else 0
Quantity Ordered tisfc001.qrdr
Quantity Positive Variance Quantity Variance if positive, else 0
Quantity Quarantined tisfc001.qqar
Quantity Ratio Quantity Delivered / Quantity Ordered
Quantity Rejected tisfc001.qtor
Quantity Scrapped tisfc001.qrjc
Quantity Variance Quantity Delivered - Quantity Ordered
Quantity to Backflush tisfc001.qtbf
Quantity to Deliver tisfc001.qtdl
Reject Ratio Bad Quantity / (Bad Quantity + Quantity Delivered)
Shortage 1 if Quantity to Deliver + Quantity Delivered is less than Quantity Ordered

0 if Quantity to Deliver + Quantity Delivered is equal to or more than Quantity Ordered

0 if Order Status is before ‘Production Completed’

(2)
  • (1) LN calculates the lead time in days according to the company calendar and availability type (using function tiint.dlltcccp.determine.lead.time.in.days for fields tisfc001.prdt, tisfc001.rdld, tisfc001.apdt, tisfc001.adld). If there is no Actual Delivery Date, the lead time is 0.
  • (2) Shortage compares the ordered quantity with the delivered quantity for production orders that have status Completed or later. But Shortage is always set to 0 for orders that have not been completed: for orders that are not yet completed, the delivered quantity is less than the ordered quantity and shortage is always 1.