Planned Activity Workbench (tsspc2610m100)

Use this session to filter the planned activities based on the values you specify and view the resource requirement lines linked to a selected planned activity. You can also filter the planned activities using the options that are based on the status of the planned activities You can also use this session to process the planned activities.

Field Information

Installation Group

The code of the installation group.

Description

The description or name of the code.

Item

The code of the item.

Serial Number

The code of the serial number.

Item Description

The description or name of the code.

Site

The code of the site.

Description

The description or name of the code.

Service Office

The code of the service office.

Description

The description or name of the code.

Operations Department

The code of the operations department.

Description

The description or name of the code.

Maintenance Scenario

The code of the preventive maintenance scenario.

Description

The description or name of the code.

Start Date

The date from when the planned activities must be displayed.

Duration

The duration for which the planned activities must be displayed.

Unit

The unit in which the duration is expressed.

Allowed values

Hours
Days
Weeks
Months
Years
Not Applicable
Filter

The date that must considered to display the planned activities.

Allowed values

Planned Start Time
Planned Finish Time
Earliest Start Time
Latest Finish Time
All

Click All to activate this filter. All the planned activities with the status Free, are displayed. LN selects the corresponding check box when you apply this filter.

Note: When you access this session, the count for each filter is displayed as 0. You must use the Refresh Total option to view the updated counts.
Before

Click Before to activate this filter. All the planned activities with the status Free, and with the date before the period specified in the Set Current Period section, are displayed. LN selects the corresponding check box when you apply this filter.

Note: When you access this session, the count for each filter is displayed as 0. You must use the Refresh Total option to view the updated counts.
Current Period

Click Current Period to activate this filter. All the planned activities with the status Free, and with the date within the period specified in the Set Current Period section, are displayed. LN selects the corresponding check box when you apply this filter.

Note: When you access this session, the count for each filter is displayed as 0. You must use the Refresh Total option to view the updated counts.
After

Click After to activate this filter. All the planned activities with the status Free, and with the date after the period specified in the Set Current Period section, are displayed. LN selects the corresponding check box when you apply this filter.

Note: When you access this session, the count for each filter is displayed as 0. You must use the Refresh Total option to view the updated counts.
All

Click All to activate this filter. All the planned activities with the status Released, are displayed. LN selects the corresponding check box when you apply this filter.

Note: When you access this session, the count for each filter is displayed as 0. You must use the Refresh Total option to view the updated counts.
Before

Click Before to activate this filter. All the planned activities with the status Released, and with the date before the period specified in the Set Current Period section, are displayed. LN selects the corresponding check box when you apply this filter.

Note: When you access this session, the count for each filter is displayed as 0. You must use the Refresh Total option to view the updated counts.
Current Period

Click Current Period to activate this filter. All the planned activities with the status Released, and with the date within the period specified in the Set Current Period section, are displayed. LN selects the corresponding check box when you apply this filter.

Note: When you access this session, the count for each filter is displayed as 0. You must use the Refresh Total option to view the updated counts.
After

Click After to activate this filter. All the planned activities with the status Released, and with the date after the period specified in the Set Current Period section, are displayed. LN selects the corresponding check box when you apply this filter.

Note: When you access this session, the count for each filter is displayed as 0. You must use the Refresh Total option to view the updated counts.
All

Click All to activate this filter. All the planned activities with the status Transferred, are displayed. LN selects the corresponding check box when you apply this filter.

Note: When you access this session, the count for each filter is displayed as 0. You must use the Refresh Total option to view the updated counts.
Before

Click Before to activate this filter. All the planned activities with the status Transferred, and with the date before the period specified in the Set Current Period section, are displayed. LN selects the corresponding check box when you apply this filter.

Note: When you access this session, the count for each filter is displayed as 0. You must use the Refresh Total option to view the updated counts.
Current Period

Click Current Period to activate this filter. All the planned activities with the status Transferred, and with the date within the period specified in the Set Current Period section, are displayed. LN selects the corresponding check box when you apply this filter.

Note: When you access this session, the count for each filter is displayed as 0. You must use the Refresh Total option to view the updated counts.
After

Click After to activate this filter. All the planned activities with the status Transferred, and with the date after the period specified in the Set Current Period section, are displayed. LN selects the corresponding check box when you apply this filter.

Note: When you access this session, the count for each filter is displayed as 0. You must use the Refresh Total option to view the updated counts.
All

Click All to activate this filter. All the planned activities with the status Canceled, are displayed. LN selects the corresponding check box when you apply this filter.