Group Sets for Projects (PCS) (tsspc2190m600)

Use this session to view and maintain the group sets generated from the group planning activity sets for Projects (PCS).

Note: 

This session is displayed only if the Group Planning for Projects (PCS) Implemented is selected.

This session is not displayed if the Planned by Origin check box for the project (PCS) is selected on the Manufacturing tab in the Resource Planning Parameters (tsspc0101m000) session.

Field Information

Start Date Groups

The start date and time of the group set. LN displays the group sets with a start date later than the specified date.

Finish Date Groups

The finish date and time of the group set. LN displays the group set with a finish date earlier than the specified date.

Group Set

The unique ID of the group set.

Activity Origin

The origin of the activities in the group sets for Projects (PCS).

Allowed values

Service Order
Work Order
Planned Activity
Project
Non-Conformance Report
Corrective Action Plan
Job Shop Order
Project (PCS)
Target Number of Groups

The number of groups you create for the group set.

Note: The value in this field is defaulted from the Attribute Group - Preferred Resources (tsspc0120m100) session.
Existing Number of Groups

The number of groups available for the group set.

Sort Method

The method to sort the activities in a group set.

Allowed values

Earliest Start
Latest Finish
Latest Start
Planned Start
Planned Finish
Respect Earliest Start Time

If this check box is selected, LN considers the earliest start time to plan the work order activity.

Note: The value in this field is defaulted from the Respect Earliest Start Time field defined in the Resource Planning Parameters (tsspc0101m000) session.
Planned Start Time

The planned start date and time of the first activity in the specified group set.

Note: This value is defaulted from the Groups for Projects (PCS) (tsspc3100m700) session, based on the groups linked to the group set.
Planned Finish Time

The planned finish date and time of the last activity in the specified group set.

Note: This value is defaulted from the Groups for Projects (PCS) (tsspc3100m700) session, based on the groups linked to the group set.
Total Activity Duration

The cumulative duration of travel for all the activities in the group set.

Note: The value in this field is defaulted from the groups (defined in the Groups for Projects (PCS) (tsspc3100m700) session) linked to the group set.