Plan Quotes (tsepp1204m000)

Use session to plan the quotes. LN creates the planned inventory transactions for the applicable cost lines.
Note: 

This session can be accessed only if the Create Planned Inventory Transactions check box is selected in the Service Quote Parameters (tsepp0100m000) session.

Field Information

Sold-to Business Partner

The From and To fields define a range of: the sold-to business partners.

Service Office

The From and To fields define a range of: the service offices..

Quote

The From and To fields define a range of: the quotes.

Start Time

The From and To fields define a range of: Planned Start Time.

Check ATP Inventory

If this check box is selected, the ATP check is performed for the inventory.

Skip Blocked Inventory

If this check box is selected, the blocked inventory is not considered during quotes planning process.

Check Planned Inventory

If this check box is selected, the planned inventory check is performed.

Check On Hand Inventory

If this check box is selected, the on hand inventory check is performed.

Scope of Inventory Check

The locations where the material availability can be checked.

Allowed values

All Warehouses in Planning Cluster

Checks if the material is available in the warehouse defined on the Material Line.

Current Warehouse Only

Checks if the material is available in one of the warehouses in the same cluster as the warehouse defined on the Material Line.

Update Planned Delivery Time of Material Lines

If this check box is selected, the Planned Delivery Time of the Material Lines is updated with the Planned Available Date when Inventory Check Status is set to Supply is late in the Service Material Availability (tstdm2520m000) session. When this check box is selected and the Check Planned Inventory check box is also selected, this check is recalculated after the update.

Update Quote (Lines) with Latest Planned Material Line

If this check box is selected, the Planned Start time of the quote or quote line of the related material line, are updated with the latest Planned Delivery time of the material lines.

Synchronize Materials with Latest Planned Material Line

If this check box is selected, the Planned Delivery time of all material lines related to the quote or quote line are updated with the last Planned Delivery time of the material lines.

Error Report

If this check box is selected, an error report is generated if the process is not completed successfully.

Process Report

If this check box is selected, a process report is generated if the process is completed successfully.