Activity - Synchronization (tppss2206m000)

Use this session to synchronize specific fields such as category, phase, and project location of the child activities with the parent activity.

Field Information

Project

The code of the project.

Plan

The code of the plan.

Activity

The code of the activity.

Activity Manager

If this check box is selected, the activity manager can be specified.

The code of the activity manager.
Note: This field is enabled only if the Activity Manager check box is selected.
Category

If this check box is selected, the category can be specified.

The code of the category.

Note: This field is enabled only if the Category check box is selected.
Business Sector

If this check box is selected, the business sector can be specified.

The code of the business sector.

Note: This field is enabled only if the business sector check box is selected.
Phase

If this check box is selected, the business sector can be specified.

The code of the phase.

Note: This field is enabled only if the Phase check box is selected.
Geographical Area

If this check box is selected, the geographical area can be specified.

The code of the geographical area.

Note: This field is enabled only if the Geographical Area check box is selected.
Project Location

If this check box is selected, the project location can be specified.

The code of the project location.

Note: This field is enabled only if the Project Location check box is selected.
Address

If this check box is selected, the address can be specified.

The code of the address.

Note: This field is enabled only if the Address check box is selected.
Options
Include Milestones

If this check box is selected, the relevant data (Activity Manager, Project Location, and Phase) in the Milestones (tppss2101m000) session is also updated based on the data specified for the parent activity.