tppin domains

Request

A request to the business partner to pay a certain amount or percentage, of the contract amount, before or after the project is initiated. This amount can be used to purchase, for example, raw materials.

Invoice

An invoice issued to the business partner as advance payment before the goods can be delivered.

Not Applicable

The advance payment is not applicable for the contract.

Fixed Fee

The amount paid to the contractor based on the terms of the contract.

Award Fee

The amount paid to the contractor in parts or as one-time payment based on the performance of the contractor.

Incentive Fee

The amount paid when the contractor meets or exceeds the performance targets.

Penalty

The amount paid to the business partner by the contractor in case the terms of the contractual agreement are not met.

Finished Activity

If the triggering activity is 100% complete or if the triggering milestone is reached, the installments is set to billable.

Specific Date

If the planned invoice date is earlier than or the same as the actual invoice date, you can set the installments to billable.

Direct
Indirect
Additional Work
Invoiced

You can print the selected range of invoiced transactions.

Not Invoiced

You can print the selected range of non-invoiced transactions.

Both
To be Invoiced

You can print the released transactions for invoicing.

Not to be Invoiced

You can print the unreleased transactions.

Both
Without Extensions

You cannot include extension transactions.

With Extensions

You can include extension transactions.

Both
Contract Award Date

The installment invoicing starts on the date when the contract is awarded.

Specific Date

The installment invoicing starts on the specified date.