Copying element budget to activity budget

You can copy the budget data from element budget to activity budget for a project using the Copy Element Budget to Activity Budget (tpptc1240m000) session. This session can be accessed only if the Use Plan check box in the Project Planning Parameters (tppss0100s000) session is selected.

Note: 
  • When you copy the element budget to activity budget, you must customize the items using the Customize Items in Budget (tpptc1255m000) session.
  • When a material budget line for which a configured generic item exists is copied, the product variant is not copied.
  • The product variant is copied for PCS items only if the budget line is copied within the same project.

When the budget line with a PCS item is copied to another project, the PCS item cannot be copied and must be replaced. If the item is derived from a standard or configured item, the item replaces the PCS item in the new project and this item must exist in the Items - Project (tppdm0505m000) session. Else, the budget line cannot be copied.

If the item is not derived from a standard or configured item, the budget line is not copied.